SL.NO |
CLIENT NAME |
PROJECT NAME |
DESCRIPTION OF WORKS |
YEAR |
| 1 |
M/s. Consolidated Contractors Co. (CCC) |
Contract No.21206-FCC-065 GC-19-KOC |
Mechanical, Sandblasting, Painting and Firber Glassing of three crude oil tanks |
May. 1992 |
| 2 |
M/s. Kuwait Shipbuilding & Rpairyard Co. (KSRC) |
KOC Gathering Center No. 15 (GC-15) |
Sandblasting, Painting, Fiberglassing and Mechanical for GC 15. |
October. 1992 |
| 3 |
M/s. Kuwait Shipbuilding & Repairyard Co. (KSRC) |
Construction of two water storage tank at STF Area No. 9W & 8W.-KOC |
Sandblasting & Painting for two huge water storage tanks |
Feb. 1993 |
| 4 |
M/s. Kuwait Shipbuilding & Repairyard Co. (KSRC) |
Construction of two water storage tank at STF Area No. TK 5W & 6W- KOC |
Sandblasting & Painting of two water storage tannks |
October. 1993 |
| 5 |
M/s. Kuwait Aviation Fuelling Company (KAFCO) |
KAFCO Tanks |
Painting for 6 Nos. of Fuel tanks 4 Nos. of Fire Water Tanks and associated Pipe works, Pumps, Filters, Valves..etc. |
Feb. 1994 |
| 6 |
M/s. Sayed Hamid Behbehani & Sons Co. |
MEW Shuwaikh Power Station |
Painting for 4Nos. Makeup Water Tanks & 1 Fire Fighting Tank and Sandblasting |
July. 1994 |
| 7 |
M/s. Ahmed Ghuloom Redha Ashkanani Est. |
Contract No.93GO42 GC-20-KOC |
Painting & Sandblasting for TK.44 GC.20 Tank, No.101 Tank NTF Tank 50 in KOC. GC.6 Tank No.1101 GC.3 Tank 1105, Tank 1106. |
Sept. 1994 |
| 8 |
Maridrive & Oil Services Co. |
Repair of KOC Single Point Morring at Mina Al-Ahmadi |
Sandblasting, Painting and Mechanical Works |
April. 1995 |
| 9 |
M/s. F & K Ibrahim Al-Shuwayer & Partners |
50,000 BBLS. Tank for Saudi Arabian Texaco Inc. |
Painting & Sandblasting and internal Fiberglass Lining |
May. 1995 |
| 10 |
M/s. The National Co. for Mech. & Elect. Works |
Project # 1066-Sabiya Power Station Tank Farm for MEW |
Painting & Sandblasting for 16 Nos of Tanks |
June. 1995 |
| 11 |
M/s. Khalifa Al-Daij Al-Dabbous & Brothers Company Limited |
Contract No. 94 GO 40 Installation of Portion of 12" Dia Gas Line from Manifold K-New to AGRP (KNPC-Shuaiba) |
Sandblasting of Pipes |
November.1995 |
| 12 |
M/s. Khalifa Al-Daij Al-Dabbous & Brothers Company Limited |
Contract No.95GO51 Modification to Supply & Distribution Pipe Works for Tanks-Ahmadi |
Sandblasting & Painting of 12" & 6" Dia Pipes |
December. 1995 |
| 13 |
M/s. Consolidated Contractors Co. (C.C.C.) |
Al-Sharq Waterfront Project |
Sand Blasting & Painting. |
May. 1996 |
| 14 |
Integral Services Co. WLL |
Equate Project-Shuaiba |
Painting & Lining of Tanks |
September. 1996 |
| 15 |
ISCOSA Industries & Maintenance Ltd |
Shipping Pum PCR-Wafra |
Blasting & Painting works |
April. 1997 |
| 16 |
Polimex-Cekop Ltd |
MEW-Sabiya Power Station |
Sandblasting & Painting works of oil and water storage tanks-16 Nos. |
March. 1998 |
| 17 |
M/s. F & K Ibrahim Al-Shuwayer & Partners |
Hand Excavation for Trunkline Pipe Support Foundations & other Foundations at SC-19 at Wafra |
Painting, Sandblasting & Wrapping of 16” Dia. SUG Trunkline |
April. 1998 |
| 18 |
M/s. Specialist Oilfield Services K.S.C. |
Subcontract CO/98/006/SBC-01 |
Internal and External Coating Services for M/S. CPECC. |
June. 1998 |
| 19 |
M/s. Kuwait Ship Building & Repairyard Co. |
Contract No. 6971-SC-01-KNPC’s Refinaries & Local Marketing Tanks Maintenance Project |
Sandblasting, Fiber Glassing and Painting of Tanks |
August. 1998 |
20 |
M/s. Specialist Oilfield Services K.S.C. |
KOC Piping Works |
Sand Blasting, Primer & Wrapping works for K.O.C. |
Feb. 1999 |
| 21 |
Kuwait Pipe Industries & Oil Services Co. |
JPME Job No.01-005-01V,02V, 03V, 04V, PWHT |
Sandblasting & Painting of Pipes and Tanks |
January. 2002 |
| 22 |
M/s. Kuwait Ship Building & Repairyard Co. |
Contract No.690013-SC-03 Supply & Erection of (6) Nos. Tanks for Effluent Water Transfer System & Minagish Water Injection Plant -KOC |
Surface Preparation, Painting and Glass-flake lining for Tanks |
July. 2002 |
| 23 |
Kuwait Pipe Industries & Oil Services Co. |
JPME Job No.01-015 (48 Vessels) |
Sandblasting & Painting of Vessels |
Augsut. 2002 |
| 24 |
Kuwait Lube Oil Company |
KLOC Tanks |
Sandblasting & Painting (Internal & External) of Tanks |
October. 2002 |
| 25 |
Al-Bahar Jacorossi Eng. & Cont. Co. |
ABJ Project. # 2050 Surge Vessel Painting |
Sandblasting & Painting of Surge Vessel |
June. 2003 |
| 26 |
M/s. John Pickle Middle East (Division of M/s. Kuwait Pipe Industries) |
JPME-Vessles |
Internal & External Sandblasting,Painting and Glassflake application for Vessel |
June. 2003 |
| 27 |
M/s. Al-Nourain Est. |
Saudi Arabina Texaco |
Tank Maintenance Project, Sandblasting, Painting & Fiber Glass works for Saudi Arabian Texaco Inc. |
July. 2003 |
| 28 |
M/s. CMN (France) |
Kuwait Naval Force |
Sandblasting, Painting & Fiber Glass works for M/s. Kuwait Naval Force. |
August. 2003 |
| 29 |
M/s.Consolidated Contractors Company (CCC) |
KOC Installation of New BS-131 & Interconnecting Lines with Gathering Centers and BS-130 |
Supply of Manpower & Equipments |
August. 2003 |
| 30 |
M/s.Consolidated Contractors Company (CCC) |
KOC Installation of New BS-131 & Interconnecting Lines with Gathering Centers and BS-130 |
Sandblasting & Painting Works |
August. 2003 |
| 31 |
M/s. Alam Steel |
Internal & External Coating of Fuel Tankers |
Sandblasting & Painting (internal & external) of Water storage & Fuel tankers |
2002-2004 |
| 32 |
M/s. Heavy Engineering Industries & Shipbuilding Company (HEISCO) |
American Vessels |
Surface preparation of American Vessels |
April. 2004 |
| 33 |
M/s. Khalid Ali Al-Kharafi & Bros Co. (KAK) |
Water & Oil Storage Tanks-Mina Al-Zour |
Sandblasting & Painting works for storage Tanks. |
July. 2004 |
| 34 |
M/s. Snamprogetti |
Installation of New BS 131 & Interconnecting Lines with GC's ND BS 130 |
Grit Blasting & Painting of Internal of Vessels (3 Nos.) |
June. 2005 |
| 35 |
M/s. Oriental Construction Co. |
Friday Market |
Painting Works |
July. 2005 |
| 36 |
M/s. Snamprogetti |
Installation of New BS 131 & Interconnecting Lines with GC's ND BS 130 |
Surface Preparation & Painting of above ground RTR Pipes |
Sept. 2005 |
| 37 |
M/s.Bin Nowiran Establishment |
Contract No.SAT-205 Cleaning of Tanks External Shell & Roof Surfaces-TEXACO |
Cleaning of Tanks External Shell & Roof Surfaces |
December. 2005 |
| 38 |
M/s. Heavy Engineering Industries & Shipbuilding Company (HEISCO) |
P.O. 8391-VT-001, Rev.0 Wet Crude Storage Tank28-TN-0202 Capacity Expansion & Medium Crude Processing-GC28 |
Surface Preparation & Coating of Bottom Plates for Tank |
July. 2006 |
| 39 |
Arabi Eneretech K.S.C. |
Contract No. JO/HC14/MP03-PMP Water Disposal Facility (MP628) - Wafra |
Sandblasting and Painting of Pipe Ends for Sleeve Joints and But Joints |
August. 2006 |
| 40 |
Al-Jazira & Quraini Transportation Co. WLL |
Tankers Job |
Sanblasting & Painting of 3 Nos. of Tankers |
September. 2006 |
| 41 |
M/s. Heavy Engineering Industries & Shipbuilding Company (HEISCO) |
KOC Contract No.25506-GC-27 Capacity Expansion for Compression and Medium Crude Processing |
Surface Preparation, Painting & Lining for Tanks |
November. 2006 |
| 42 |
Kuwait National Petroleum Co. |
Contract No.CA/1044/LVC |
Repair & Coating of FRP Tank |
Feb. 2007 |
| 43 |
Arabi Eneretech K.S.C. |
Contract No. JO/HC32/MP04 -SUG Facilities Upgrade Project |
Blasting & Painting (Internal & External) and Wrapping of above Ground Piping, Pipe line & Fittings. |
Feb. 2007 |
| 44 |
Arabi Eneretech K.S.C. |
Contract No. CB/PD/1170 Hydrogen Makeup Compressor Project in Unit-18 |
Blasting & Painting works of refabricated pipe spools and structural steel members |
March. 2007 |
| 45 |
M/s. Heavy Engineering Industries & Shipbuilding Company (HEISCO) |
Contract No. CA/PD/3642-Replacement of 12 Nos. of off site pipelines in Old Refinery at MAA |
Grit Blasting & Coating/Wrapping of Pipes |
January. 2007 |
| 46 |
M/s. Sayed Hamid Behbehani & Sons Co. |
New Shuwaikh Garage |
Supply and Apply Paint for Metal Decks & Joists |
March. 2007 |